Getting deposit bac...
 

  You don't need to be an 'investor' to invest in Singletrack: 6 days left: 95% of target - Find out more

[Closed] Getting deposit back from builder after canceling

124 Posts
62 Users
0 Reactions
2,071 Views
Posts: 0
Free Member
Topic starter
 

You can probably tell where this is going, and I'm hoping someone in a similar situation has some suggestions on how to deal with this.

So following on from this we've had a change in circumstances which mean we're not going to do the building work we set in motion.

We signed a contract with the builder in late November 2021 and paid around a 5% deposit, for a slot to start work in late March/April 2022. The builder at that point said they'd not even be thinking about the build until after Christmas. In January it turned out we didn't want to go ahead with the building work, and got in touch with the builder to tell them to stop. The builder was understandably a bit miffed, saying they'd turned away other work (10 jobs according to them), but they'd get in touch in a couple of weeks to let us know what was going on.

Two and a half weeks later, we got in touch again to discuss the deposit, and they say they're not going to return it. Reasons cited were that they tended to order materials like bricks in bulk (there is no bespoke stuff for this build) from their supplier for preferential pricing, and that they'd had to let go of a couple of their contractors due to our work no longer going ahead.

I've had a look at the contract, which is a template one from the Foundation of Master Builders and it is pretty basic. From my interpretation, your right of cancellation with no reason is 14 days from signing the contract. This has lapsed, so it does not apply. It also mentions they can subtract the loss of value for any goods delivered to us. Which they weren't. There is no mention of the deposit being non-refundable.

From a common sense perspective, we let the builder know immediately and well in advance of the start date of the cancellation so they'd not be blind-sided. There was an outside chance we may have been able to carry on with the build, but with lead times and the demand for their work, we didn't want to cancel at the last minute. We also didn't expect them to refund our deposit in full, but would have been happy to pay for any work they'd done so far, which I frankly think they've not.

Legally, it seems that requesting their supplier (one of the large merchants think Jewsons etc) to hold inventory for them isn't enough cause to withold the deposit. Neither is having to let go of subcontractors as that's partly why you employ contractors. They've not delivered anything of value to us yet, so at most, the only thing they could point at having done for us is perhaps planning a schedule for work and putting an order in for some materials. Contractually, it looks like they are obliged to notify us of any materials ordered which they have not done.

I don't know how far in advance orders need to be made, or what the cancellation policy is from their supplier. There's also a chance they could reuse the materials on a different job.

It looks like theo only option now, is to file a claim through small claims court for the return of the deposit. I've already gotten in touch with a solicitor and the idea is we draft a letter of intent, and then go through the legal process if this doesn't work. The builder is a local one, and used to live in my neighbourhood, so they're not someone who can do a runner easily. They also look like they have the means to pay back the money if the claim succeeded.

Congrats if you've made it this far!

TL;DR: Paid a deposit to builder to build a gin palace in November and signed a contract. Work was supposed to happen in March/April. Cancelled the build works in early January. Builder is efusing to return any of the deposit which is an amount enough to buy a very nice bike. Can we expect to see any of our money back?


 
Posted : 02/02/2022 1:04 pm
Posts: 7270
Free Member
 

There is no mention of the deposit being non-refundable.

Is there is any mention of it being refundable (other than for cancellation with 14 days of signing)?


 
Posted : 02/02/2022 1:14 pm
Posts: 0
Free Member
 

In my experience there at a no point messing about with anything other than speaking to a solicitor. Once they’ve looked at the contract then if they think your case is decent, I would imagine a letter before action. That may or may not do the job. If not then next stop is court.

From what you’ve said, and only from what you’ve said it sounds like they are trying it on.


 
Posted : 02/02/2022 1:15 pm
Posts: 3204
Free Member
 

In short "no". If you are able to get it back then that should be included in your application to appear on The Apprentice.


 
Posted : 02/02/2022 1:17 pm
Posts: 4954
Free Member
 

Your deposit was to hold your place and any initial expenses. You decided you are not doing the work. The builder has still organised their self around this schedule, pre ordered material. This is all still work that has been done, there may not be anything physical but work has been done on your job. Storage of martials cost money if it is to be used on another job as you suggest. So, from a common sense perspective, I would not expect a full refund but perhaps 50% if I was lucky, and would approach them about that basis.


 
Posted : 02/02/2022 1:18 pm
Posts: 12865
Free Member
 

I’ve no idea who came up with the idea of “refundable deposits”, surely the whole point is you’re making a commitment and they [i]aren’t[/i] refundable? I think you’ll find that’s the default position legally, I.e. it doesn’t have to say it’s non-refundable, because that’s what a deposit is! The builder will have incurred costs, even if just time, and will have turned away other work for you (even if he’s exaggerating this!)


 
Posted : 02/02/2022 1:26 pm
 cp
Posts: 8928
Full Member
 

I don't get why people expect all or some of a deposit back. Otherwise what the hell is the point of the deposit. It's a commitment from the buyer to the supplier. If the supplier bails, fair enough, deposit returned. If the buyer bails, deposit gone. Simples surely?


 
Posted : 02/02/2022 1:30 pm
Posts: 4588
Free Member
 

Tough sh!t I reckon, a deposit is typically non refundable unless it states its refundable.

Next time understand what the real purpose of a deposit is.

It sounds like you're being pretty unfair to the builder by going legal in an attempt to get it back. The deposit is a commitment (a statement of confidence if you like ) from you to enable the builder to start the process of doing your job, if you pull out they keep the deposit. For them to start doing your job they will have had to turn down other work, order materials , put in place hiring of subbies - potentially paying then up front to lock them into a date etc.


 
Posted : 02/02/2022 1:30 pm
Posts: 5164
Free Member
 

To be fair, i'd be happy that it was only a 5% deposit, reality is there are so many variables in this, you need to work out if it's worth fighting, that would be my first step, then work out the best way forward from that.


 
Posted : 02/02/2022 1:30 pm
Posts: 13617
Full Member
 

In the current market of supply chain issues it's highly likely they've secured materials for a build that's due to start in a few weeks. Especially if it's a good sized job which is what it sounds like it is.

And the bricks, timber and other materials for your project probably won't be able to be used on another job for ages - a brick isn't just 'a brick'. So where will he store those? The back of his van?

I’ve no idea who came up with the idea of “refundable deposits”, surely the whole point is you’re making a commitment and they aren’t refundable?

Ad-men for people like DFS! Then followed by pages of legal guff highlighting why you can't have it back.

You'll be lucky to get half back, if any.


 
Posted : 02/02/2022 1:32 pm
Posts: 0
Free Member
 

This may turn into a careful what you wish for moment if they end up tallying up costs to show why they're not returning it and they come out above your deposit amount.


 
Posted : 02/02/2022 1:32 pm
 db
Posts: 1922
Free Member
 

Honestly walk away. I don't think you will come out of this better off and the only people who will make money are solicitors.


 
Posted : 02/02/2022 1:36 pm
Posts: 10333
Full Member
 

As above really, your deposit saved a space in his calendar and lead times for materials are silly at the moment so they'll have ordered in advance.

Other things like pricing your job takes time, and is costing him money if they get nothing from the job.

Be nice, and you might get something back if he manages to fill your space with another job and can use/cancel materials.


 
Posted : 02/02/2022 1:42 pm
Posts: 13916
Free Member
 

In the current market of supply chain issues it’s highly likely they’ve secured materials for a build that’s due to start in a few weeks.

Although I've not come across a building supplier that doesn't accept returns (i.e. Jewson gives 30 days).
That said.... the sub-contractor bit is total rubbish and a "deposit" is probably non-returnable - certainly not 100% of it.


 
Posted : 02/02/2022 1:47 pm
Posts: 7618
Free Member
 

Joiner I had doing some work was late because previous people were cancelling a big job and upset that they weren't getting deposit back. He went round to explain that they were about to be more upset when the windows arrived in a week's time because the window co expect payment as per the customer's stipulation in the contract.


 
Posted : 02/02/2022 1:49 pm
Posts: 2386
Free Member
 

If I changed my mind for any reason, I'd expect to lose my deposit.

What would be the point of any deposit if that wasn't the case?

Why are you expecting to get it back? Why should you? (Apart from the fact that you'd like it back, because money.)


 
Posted : 02/02/2022 1:50 pm
Posts: 56564
Full Member
 

The builder was understandably a bit miffed, saying they’d turned away other work (10 jobs according to them), but they’d get in touch in a couple of weeks to let us know what was going on.

I think that as a self-employed person I'm going to be pretty frank and quantify and put in perspective the phrase 'a bit miffed' from the builders side.

I've had people do this. "Can we book you in for a few weeks at *insert date here*". Then I get further phone calls from different clients saying are you available *insert date here*?. No I'm afraid I'm not. I'm already booked for those few weeks.

Then, at the 11th hour (and if you're organised then yours qualifies as the 11th hour) you phone them to check up that its all going ahead and get "actually, no, theres a couple of jobs which we were expecting that haven't come in yet, so we don't need you after all"

I'm sure that he felt the same as I did, having turned away other work on the strength of it and now looking at having to find weeks worth of work. And I hadn't even spent work on materials

So let me tell you that 'a bit miffed' is actually ABSOLUTELY *ING LIVID!!!" and that when you said the job wasn't going ahead he'll have been calling you every * under the sun, believe me.

And then when you asked for your deposit back he'll have had to have been physically restrained by his wife from coming round and squaring up to you for absolutely taking the ****ing piss.

I'd cut your losses if I were you, take it on the chin and accept the fact that you signed a contract which you are now no longer honouring, and maybe in future have a bit more thought and consideration to the very real implications your decisions have on others

Sorry to be blunt, but I reckon the above is a pretty accurate and honest reflection of the present situation from his perspective.

Whatever your reasons for not proceeding, you are asking somebody else to take a substantial financial hit and then go through the ball-ache of reorganising their schedule/materials orders because you're no longer honouring a contract that you signed


 
Posted : 02/02/2022 1:52 pm
Posts: 0
Free Member
 

You've broken a contract. The builder is entitled to recover their costs to-date and their loss of profit on the contract.

I'd let it drop, you may find they counter-claim more than the 5% they're asking for at the moment.

Talk to Citizen's advice if you don't want to pay for a solicitor.


 
Posted : 02/02/2022 1:55 pm
Posts: 1955
Free Member
 

What size deposit are we talking (5% of how much)?

And why isnt the building work going ahead?

Not that you have to say, im just being nosey.


 
Posted : 02/02/2022 1:56 pm
Posts: 2191
Free Member
 

I agree with the others saying walk away and leave it at that - a deposit is not intended to be refundable by definition and you've exceeded the 14 day exemption to this. It is extremely unlikely that the builder hasn't incurred costs in terms of making and receiving materials in advance of your work especially in the current situation which is fairly desperate in the material supply game.

You're lucky it was only 5%, more and more companies are requiring up to 50 percent in advance payment now to even secure any kind of delivery date at all.

It's shit, but it's the way things are now.


 
Posted : 02/02/2022 1:57 pm
Posts: 0
Free Member
 

curiousyellow
Free Member

You are in the wrong here fella, let the deposit go.


 
Posted : 02/02/2022 1:58 pm
Posts: 13617
Full Member
 

And why isnt the building work going ahead?

I think this is the key...

If it's due to serious illness or job-loss you may be able to appeal to their better nature.

If it's just because you don't fancy it anymore or have done your sums wrong, then tough.


 
Posted : 02/02/2022 1:58 pm
 db
Posts: 1922
Free Member
 

Do remember if you lose the small claim (and you might) the builders costs can go against you. Can you afford this?


 
Posted : 02/02/2022 2:00 pm
Posts: 40225
Free Member
 

I think it'd be more reasonable to try to have a civil discussion about costs incurred and try for a compromise in acknowledgement that they are likely to be able to use any materials purchased, but that there have been costs to them in terms of planning, procurement and time spent arguing with you.

But basically I wouldn't expect to get a deposit back if I'd just changed my mind.


 
Posted : 02/02/2022 2:06 pm
Posts: 0
Free Member
Topic starter
 

@mefty the contract makes no specific mention related to the deposit. Interestingly, when approached, they referred to the contract.

@TheBrick I understand your point about materials storage. Contractually, the builder is obliged to notify us of any materials ordered for our work. We have had no notification of any costs. I'd be happy to try and offer a compromise but I'm not confident of reaching one. In any case, the legal route offers a mediation service.

@argee yes, I'm definitely not interested in any prolonged legal issue. However, we worked hard to earn that money. If they've done work for us for that amount of money, then I'd like to understand what it is.

@the-muffin-man they said they're not going to even think about the job until after Christmas and we've had no contact from them since signing the contract last year. I'm assuming if there was money due, they would be invoicing us for it (which according to the contract they are).

@db I'm definitely not interested in fattening anyone else's bank balance. However, seeing that the contract is what the builder is referencing and it makes no mention of the deposit I would like to know where I stand.

@binners thanks. That certainly puts things in perspective. It's not a decision we came to lightly, I assure you.

Looking at the contract from a purely legal standpoint (and I am not a lawyer) keeping the entire deposit without performing any work, without evidence of materials being ordered for it feels like a disproportionate penalty.


 
Posted : 02/02/2022 2:08 pm
Posts: 0
Free Member
 

Looking at the contract from a purely legal standpoint (and I am not a lawyer) keeping the entire deposit without performing any work, without evidence of materials being ordered for it feels like a disproportionate penalty.

Not performing any work? Mate the guy will have been planning your extension, doing pricing, sorting out staff, placing orders etc etc. And now as well as cancelling all that, they've got to go out and fill in a few weeks gap in their schedule that you've now left them with.

5% is more than reasonable.


 
Posted : 02/02/2022 2:12 pm
Posts: 13617
Full Member
 

Brew anyone!? Could be a long one!...

[img] [/img]


 
Posted : 02/02/2022 2:16 pm
Posts: 0
Free Member
Topic starter
 

@seosamh77 the only pricing supplied so far was as part of the initial quote. I'm not saying for one second that they've done absolutely nothing and I've worded my previous post badly. Given the advance notice (close to 3 months), I'd have hoped they could bring work forward to fill the schedule, or obtain new work given the demand. I realise they're not obliged to do so.

@the-muffin-man I did laugh at that. Thanks!


 
Posted : 02/02/2022 2:18 pm
Posts: 77347
Free Member
 

It's not a penalty though, is it. A deposit is a sign that you're committed to undertaking the work. If you could just go "sorry, changed my mind, I'll have my money back thanks" months later then there would be little point in asking for a deposit in the first place.

What costs the builder may or may not have incurred is an irrelevance. "Reasons cited" is an irrelevance, they don't owe you an explanation. You are in breach of contract. Fin.

You might get lucky. The builder might be receptive to extenuating circumstances or even just to you asking nicely. But I highly doubt that going legal will make either party any richer. Sorry.

Why aren't you going ahead with it?


 
Posted : 02/02/2022 2:22 pm
Posts: 0
Free Member
 

I’d have hoped they could bring work forward to fill the schedule, or obtain new work given the demand. I realise they’re not obliged to do so.

Bringing work forward still leaves them with a gap to fill elsewhere.


 
Posted : 02/02/2022 2:23 pm
Posts: 7751
Free Member
 

Gov.uk website information on deposit refunds for goods and services -
https://www.gov.uk/government/publications/cancelling-goods-or-services-guide-for-consumers/cancelling-goods-or-services

Based on what you posted the builder doesn't appear to have made attempts to defray the cost of any materials actually purchased; your cancellation gives him the potential to pull other jobs forward - has he done that; his claim about subbies doesn't stack up but managing/retaining subbies is his problem, not yours.

You are within your rights to ask for evidence of advance purchase materials with evidence that he cannot return them or cancel any orders; there may be a cancellation or returns charge but it's for the builder to prove that to you.

Have you contacted the federation of master builders to question how robust their contract template is?
Is a 14 day no fault cancellation clause reasonable - in stricty legal terms?
The template will have been written 100% in favour of the contractor and assumes a client will neither read nor challenge it.

Don't walk away from this without having a good go at recovering your money.


 
Posted : 02/02/2022 2:27 pm
Posts: 77347
Free Member
 

Well, I sit corrected.


 
Posted : 02/02/2022 2:29 pm
Posts: 20561
Free Member
 

To be fair, i’d be happy that it was only a 5% deposit

So much this. Don't be a dick and accept your loss.

Bringing work forward still leaves them with a gap to fill elsewhere.

Unless they are not very good at all, they will soon fill in any gaps with the market the way it is at the moment.


 
Posted : 02/02/2022 2:33 pm
 Aidy
Posts: 2941
Free Member
 

Gov.uk website information on deposit refunds for goods and services –
https://www.gov.uk/government/publications/cancelling-goods-or-services-guide-for-consumers/cancelling-goods-or-services
/blockquote>

Non-refundable deposits should only be a small percentage of the total price.

5% seems like a small percentage to me.


 
Posted : 02/02/2022 2:34 pm
Posts: 7751
Free Member
 

Also see
https://www.which.co.uk/consumer-rights/advice/can-i-claim-back-a-non-refundable-deposit-aHwOj3S21AWP

Note the references to unfair contract terms.


 
Posted : 02/02/2022 2:34 pm
Posts: 0
Free Member
Topic starter
 

@Cougar definitely asked nicely. I don't feel comfortable discussing why it's not going ahead unfortunately.

@seosamh77 good point. I'd have hoped one of the jobs they'd turned away would match the gap left, or soften the blow. It doesn't seem like the worst time to have work fall through judging by the amount of construction going on around me right now.

Could I try and understand why the legal approach is being met with opposition? If I were in a position where work had commenced and I was unable to pay, then I'd not expect the builder to swallow the loss if they thought they could recover their money that way.


 
Posted : 02/02/2022 2:34 pm
Posts: 15068
Full Member
 

I'm not sure any legal argument would even get as far as the builder having to justify keeping the deposit with mateials orders etc.

Really you paid the deposit to secure the job to be done - it was secured.

Think of it another way, if you put a deposit down on a package holliday and then decide you don't want to go...what would you expect the outcome to be?


 
Posted : 02/02/2022 2:36 pm
Posts: 7751
Free Member
 

5% seems like a small percentage to me.

Is taken completely out of context; read the guidance in full.


 
Posted : 02/02/2022 2:36 pm
Posts: 0
Free Member
Topic starter
 

@frankconway thank you!

@Aidy it's still money we've had to work hard for.

@johndoh I don't understand the position here. If they can find work to fill the gap they'd not have lost any money. At that point, is it still acceptable to retain a deposit in that case?


 
Posted : 02/02/2022 2:40 pm
Posts: 7751
Free Member
 

matty - refer to the gov.uk website and read the Which guidance; these are published to help ensure clients/customers are not subject to unreasonable/unfair contracts and have a better understanding of their legal rights.

The OP has the legal right to pursue this - and should.


 
Posted : 02/02/2022 2:44 pm
Posts: 0
Free Member
 

Is taken completely out of context; read the guidance in full.

Not really, "a non refundable deposit" in that guidance is clearly different from a cancellation charge.

That's not to say the OP has to roll over and accept that the deposit is non-refundable just that is not the same as a cancellation charge.

Really a lot of this will be down to the money involved, if the deposit is on a few grand of work it's probably not worth the time to fight it from the builder's point of view if the OP decides to go down the legal/shouty route.

If it's on a few 10s or 100s of thousands it probably is but at that stage, it's unlikely they'll struggle to provide the evidence required to at least make this a visit to court, at which point the OP needs to consider this might well end up much more expensive expensive than 5%.

As I said above, careful what you wish for.


 
Posted : 02/02/2022 2:44 pm
Posts: 10333
Full Member
 

your money.

It's not his money until he has proved or the builder hasn't proved he incurred those costs. At the moent the OP has paid a depsoit and broken the contract.


 
Posted : 02/02/2022 2:44 pm
 Aidy
Posts: 2941
Free Member
 

@Aidy it’s still money we’ve had to work hard for.

I wasn't saying it wasn't. I was just quoting the gov website guidance.


 
Posted : 02/02/2022 2:46 pm
Posts: 0
Free Member
 

curiousyellow

@johndoh I don’t understand the position here. If they can find work to fill the gap they’d not have lost any money.

If they find work to fill the gap(they more than likely will), are you willing to pay the difference if it's not to the same value?

Just saying you seem to be making a lot of assumptions that this is cost neutral to the builder.


 
Posted : 02/02/2022 2:47 pm
Posts: 0
Free Member
 

. If they can find work to fill the gap they’d not have lost any money. At that point, is it still acceptable to retain a deposit in that case?

That depends, if they pull forward a job from two months later than yours they fill your space, but they might not then fill the space in two months, it's only really filled if there's new work to plug the gap.

Those other jobs may also need things which can't arrive in time and so on. They might need twice the amount of hours your job did, or half and so on.

In theory it's all easy. In practice, who knows.


 
Posted : 02/02/2022 2:49 pm
Posts: 7270
Free Member
 

There is no provision for repayment so therefore you are essentially arguing it is a penalty or unreasonable amount, I think you will struggle to find anyone who would think a 5% deposit is unreasonable.


 
Posted : 02/02/2022 2:53 pm
Posts: 13330
Full Member
 

See, for me, I see that as a deposit to secure services, which you've done. That you decide not use those services then that's your issue and not his.
He may feel generous and give you some back, but he equally may not.

@Aidy it’s still money we’ve had to work hard for.

As has the builder, quoting, designing, organising and materials.


 
Posted : 02/02/2022 2:54 pm
 Aidy
Posts: 2941
Free Member
 

Even if they can fill the slot, there's still all the admin they had to do to price up the job, order materials, schedule sub-contractors. It's not inconceivable that they'll have cancellation charges to pay themselves.


 
Posted : 02/02/2022 2:56 pm
Posts: 15068
Full Member
 

matty – refer to the gov.uk website and read the Which guidance; these are published to help ensure clients/customers are not subject to unreasonable/unfair contracts and have a better understanding of their legal rights.

The OP has the legal right to pursue this – and should.

From what I can see, the OP would only be entitled to a refund of the deposit if the contract was unfair - I'm not seeing how it was unfair, the deposit is to cover risk for the builder in exctly an event like this, or if the builder cancelled, breaking the contract.

It's the OP who appears to be breaking contract?


 
Posted : 02/02/2022 2:56 pm
Posts: 4985
Full Member
 

See, for me, I see that as a deposit to secure services, which you’ve done. That you decide not use those services then that’s your issue and not his.

This is my thinking, BUT if the contract doesn't reflect that and you have no ethical qualms pursuing it, then you should.

What is right and what the contract says/allows can often be different.


 
Posted : 02/02/2022 2:58 pm
 wbo
Posts: 1669
Free Member
 

One point of the deposit is so that once you've booked a place in their schedule you don't muck around and cancel without suffering a penalty. That's happening here.


 
Posted : 02/02/2022 3:11 pm
Posts: 4588
Free Member
 

OP - at what point in time would you consider it ok for them to keep your deposit if you cancelled?

or is the answer - its never ok to keep my deposit.


 
Posted : 02/02/2022 3:29 pm
Posts: 77347
Free Member
 

I don’t feel comfortable discussing why it’s not going ahead unfortunately.

With us or with the builder?

With us, fair enough. With the builder though, if there are extenuating services then you may need to decide when is more important to you, feeling uncomfortable or getting your money back. I would hope that any reasonable tradesman would appreciate the difference between "we don't want you to do the work any more because I can't be arsed" and "we can't go ahead with the work because the money had to go on granny's funeral costs."


 
Posted : 02/02/2022 3:33 pm
 glp1
Posts: 36
Free Member
 

For my sins I'm an architect, one piece of advice I give any potential client I go to see whether I am employed by them or not is do not pay anything upfront. sorry you probably don't want to be told that.
There is no reason to do so - all contractors have trade accounts - these are paid for 30+ days down the line from order.

You did right by using a contract at least - never ever start a job without a contract, the other pice of advice any other competent professional would give.

Federation of master builders contract is okay, I use the JCT Homeowners Contract - plain English campaign endorsed and very simple to use & fill out. I use it for 90% of the domestic jobs I do.

Getting your deposit back, I think you'll be lucky as the contract says 14 days and this has passed.

However, you should have been talked through the contract by the person proposing it (I do this to ensure all clients are aware of what they are signing upto - I am required to do this to avoid any misunderstanding by a client and would if it went to court explain why I choose that contract). You should have then had it explained to you why this contract was appropriate for the job concerned. If you didn't a solicitor might be able to argue that you didn't understand the conditions / weren't made aware of them.

hope this helps


 
Posted : 02/02/2022 3:39 pm
Posts: 0
Free Member
 

I sincerely doubt that a contract produced by the FMB will be judged 'unfair'. (& was the 5% deposit in the contract anyway??)

As I said further up, if you break a contract then you're liable for the other party's loss of profit and direct cost.

5% is cheap in my opinion (they were probably hoping to make 5% profit on the job and will be able to show some direct costs too (time spent by management etc)).


 
Posted : 02/02/2022 3:45 pm
Posts: 8613
Full Member
 

one piece of advice I give any potential client I go to see whether I am employed by them or not is do not pay anything upfront. sorry you probably don’t want to be told that.

But surely that relates more to paying for materials up front etc.? I'd say a deposit is different, just to hold a place in a queue and to cover any pre-job costs would be enough to justify a 5% deposit.

If I were in the OPs position I can see why it stings and it's hard to just let go (especially if that 5% is in the £thousands) but given it was a deposit to secure the builder's services and not to cover material costs etc. I really don't see how you can think it's reasonable to expect the deposit to be returned. Sure, it's worth asking as the builder may throw you a bone but if they've said no then it's time to walk away.


 
Posted : 02/02/2022 4:18 pm
Posts: 0
Free Member
 

As someone who buys a lot of materials in big and small quantities the worst restocking fee I have ever had was 5%. And many builders merchants are currenty short of materials and waiving all restocking fees.
OP needs to heed advice above and should only pay for the builders proven loss.


 
Posted : 02/02/2022 4:40 pm
Posts: 15068
Full Member
 

There will be intangible costs though, if the builder subbed out a roofer and a sparky for example, thier time has essentially been wasted too and there's also loss of reputation of the builder has cancelled the subbies etc. etc.

What are the OPs actually grounds for wanting the deposit back?
"I want some money" isn't sufficient grounds.


 
Posted : 02/02/2022 4:47 pm
Posts: 9135
Full Member
 

If he's prebought the materials, dont those now belong to you ?.


 
Posted : 02/02/2022 4:48 pm
 poly
Posts: 8699
Free Member
 

@johndoh I don’t understand the position here. If they can find work to fill the gap they’d not have lost any money. At that point, is it still acceptable to retain a deposit in that case?

Robust legal advice on that point is likely to cost more than your deposit! Note that the CMA says they can charge you for loss of profit as well as direct costs etc... Reshuffling the jobs is not without its costs. Someone has to call all the people in the pipeline, someone has to call all the suppliers, someone has to contact the subbies who were lined up to do the plumbing or electrics, that's a lot of moving pieces any of which can trip you up and make you go back to the start, cost you more etc.

Does the contract have an arbitration or dispute resolution clause? I'd expect a trade association in construction to have something like that. Beware - depending what it says talk of going to court may at least be premature, and in some cases make going to court the worst course of action.

For my sins I’m an architect, one piece of advice I give any potential client I go to see whether I am employed by them or not is do not pay anything upfront. sorry you probably don’t want to be told that.
There is no reason to do so – all contractors have trade accounts – these are paid for 30+ days down the line from order.

That's handy, I'm thinking of remodelling the house - could you pop over and do some drawings for me.

do you credit check domestic clients? probably far more effective to ask them for 5% upfront - the dreamers, people with no money, or no agreement from the other half to spend the money, or who need to sort out a loan are suddenly forced to get things in order.

However, you should have been talked through the contract by the person proposing it (I do this to ensure all clients are aware of what they are signing upto – I am required to do this to avoid any misunderstanding by a client and would if it went to court explain why I choose that contract). You should have then had it explained to you why this contract was appropriate for the job concerned. If you didn’t a solicitor might be able to argue that you didn’t understand the conditions / weren’t made aware of them.

. They MIGHT, but equally I'd never take legal advice from the person providing a contract or a builder in general. It might be appropriate to get advice from an architect on the type of contract used to manage a building project, and the architect's professional body might expect him to advice the client on the suitability of that contract, but the builder almost certainly has no such professional obligation. If the sum of money is large enough then of course it would have been wise to ask a solicitor to review the contract - how big that sum is will depend on your own circumstances. However, builders are busy enough to walk away from clients who challenge their contracts just the same as they can walk away from clients who won't pay 5% up front. I'm surprised all your clients can afford to be that selective in the current market.


 
Posted : 02/02/2022 4:55 pm
Posts: 0
Free Member
 

If he’s prebought the materials, dont those now belong to you ?.

I've now got an image of the OP pranging their car as they turn into the drive and find 10 palette of bricks that weren't there in the morning.


 
Posted : 02/02/2022 4:56 pm
Posts: 3204
Free Member
 

OP. If you do get anything back i'd be interested to know how so please report back when you are done. Cheers


 
Posted : 02/02/2022 5:07 pm
Posts: 7670
Free Member
 

We get one of these every few months. In my minds eye/imagination, I see a self entitled snowflake wah waahing at the unfairness of it all; 'but why won't he/she just roll over for me? It's so unfair...' etc.

Yeah it's right someone else should take a swift kick to the plums and absorb your indecisiveness just because you've changed your mind. Fkc the change of circumstances, they're not the builders fault... How about if he came back to you asking for more £££'s or time as his situation had changed. How accommodating do you think you'd be?

Wasn't it Geordie Mick last time with car purchases or some such?


 
Posted : 02/02/2022 5:25 pm
Posts: 12993
Free Member
 

I’ve not come across a building supplier that doesn’t accept returns

A lot of places won't be paying back 100% refund. Pick up /delivery costs, etc.

If I were the contractor (I am, but not for op) I'd be keeping the deposit and saying go swim.


 
Posted : 02/02/2022 5:29 pm
Posts: 477
Free Member
 

I got the distinct impression when we had our extension done that there wasn’t a huge amount of planning ahead by the builder, and he relied heavily on the merchant delivering next day. This was in 2020 so there were materials shortages due to covid.


 
Posted : 02/02/2022 5:30 pm
Posts: 7751
Free Member
 

So many bullish comments qbout someone else's money - most ignoring legal rights and government guidance.
The OP's builder is likely thinking...they won't challenge, they'll swallow losing the deposit.
I'm very clear about what I would do - and how and why - and it doesn't involve rolling over for a builder.


 
Posted : 02/02/2022 5:38 pm
Posts: 7670
Free Member
 

I wouldn't get too excited about 'Govt guidance'. Have you seen them?


 
Posted : 02/02/2022 5:39 pm
Posts: 12865
Free Member
 

It’s very telling from these comments who’s been self-employed/run a business or understands what that entails, versus those who just look down their nose at the “little people” such as tradesmen, business owners etc - who have the bare-faced cheek to try to earn a living for themselves and try to support their families, employees etc and should just be bloody grateful that you even [i]considered[/i] using their services as it is your god-given right to piss them about as you see fit 😉


 
Posted : 02/02/2022 5:44 pm
Posts: 20561
Free Member
 

and it doesn’t involve rolling over for a builder

So the builder should roll over for an individual because they have changed their minds despite committing to the work? I am glad I don't meet people like you in my business.


 
Posted : 02/02/2022 6:09 pm
Posts: 2737
Free Member
 

It’s very telling from these comments who’s been self-employed/run a business or understands what that entails, versus those who just look down their nose at the “little people” such as tradesmen, business owners etc – who have the bare-faced cheek to try to earn a living for themselves and try to support their families, employees etc and should just be bloody grateful that you even considered using their services as it is your god-given right to piss them about as you see fit 😉

Very much this... you win the internet for me today


 
Posted : 02/02/2022 6:15 pm
Posts: 15068
Full Member
 

I'd be really interested to hear how this plays out -

deposit which is an amount enough to buy a very nice bike

let's say a very nice bike is £2500, that's 5% of £50k, so it's a substantial building job that would require a lot of planning, prep, more than likeley the builder would need to sub parts of the job out to other tradesmen collegues, so before we even get onto materials, theres an administration/project management overhead.

I think it would be pretty easy for the builder to reasonably assert £2.5k in lost man hours, reputation, materials, general faffing about cancelling subbies, and any costs associated with that..

I wonder what the OPs solicitor has said about chances of success? I can't see it personally, but IANAL.


 
Posted : 02/02/2022 6:18 pm
 Aidy
Posts: 2941
Free Member
 

I think some of it might depend on how much 5% actually is. If it was £2k, I can kinda see that the builder might have incurred those kinda costs. If it was £20k, I can see why you might want some of it back.

OTOH, 5% is 5% - more expensive projects have more expensive up front costs and planning.


 
Posted : 02/02/2022 6:23 pm
Posts: 13916
Free Member
 

he relied heavily on the merchant delivering next day.

They do.
And in the unlikely situation that the builder has already bought materials using the deposit then those materials belong to the OP.

there’s still all the admin they had to do to price up the job

Quoting costs money but companies quote for jobs all the time and never get them.... That's just part of running a business.
If the OP asked for prices from 5 companies, then 4 of them would have incurred costs with for no return.


 
Posted : 02/02/2022 6:28 pm
Posts: 20675
 

I amazed anyone sees ‘non refundable deposit’ on a contract, signs it thinking ‘yeah but not really 😏’.


 
Posted : 02/02/2022 6:28 pm
Posts: 15068
Full Member
 

Put the shoe on the other foot, you get commissioned to do a chunky bit of work, clear your calander to do it, losing out on other potential jobs and not only does the customer cancel, they expect thier deposit back?

I can't see that that will fly in court.


 
Posted : 02/02/2022 6:35 pm
Posts: 8035
Free Member
 

What’s the point of tradesmen taking a deposit if you can just cancel and demand it back on your whim?

I don’t understand what you thought the deposit was for if you though that was the case?

Also, what zilog said.


 
Posted : 02/02/2022 6:37 pm
Posts: 15068
Full Member
 

I think some of it might depend on how much 5% actually is. If it was £2k, I can kinda see that the builder might have incurred those kinda costs. If it was £20k, I can see why you might want some of it back.

OTOH, 5% is 5% – more expensive projects have more expensive up front costs and planning.

Very good point actualy, but we can only speculate as we don't have that information.


 
Posted : 02/02/2022 6:39 pm
Posts: 2191
Free Member
 

Quoting costs money but companies quote for jobs all the time and never get them…. That’s just part of running a business.
If the OP asked for prices from 5 companies, then 4 of them would have incurred costs with for no return.

That's correct, except that's not what's happening here is it. Companies offer free quotations and until accepted you aren't in contract with them hence they aren't entitled to any monies if you decide not to pursue it any further.

As the OP was now in contract with the builder he is subject to the terms of that contract which (although we haven't seen the actual contract) seems to say a deposit is refundable within 14 days, which has been exceeded.

Anything more than that regarding deciding what actual loss may have been incurred if any by the builder is academic unless he chooses to involve dispute resolution or litigation, surely?


 
Posted : 02/02/2022 6:44 pm
Posts: 2191
Free Member
 

Having had a look at a cheekily uploaded version of the federation of master builders contract which is stated was used, I can't actually see anything relating to a deposit being due so I'm not sure why OP has paid a deposit in the first place.

Would be good to get some clarity from the OP on the payment terms in this contract.


 
Posted : 02/02/2022 6:52 pm
Posts: 3899
Free Member
 

"Would be good to get some clarity from the OP on the payment terms in this contract."

IT would be good to get some clarity on his moral compass...


 
Posted : 02/02/2022 6:58 pm
Page 1 / 2

6 DAYS LEFT
We are currently at 95% of our target!